Training Center Office of Transport and Communications University – Ho Chi Minh City in Vung Tau
Training Center Office of Transport and Communications University – Ho Chi Minh City in Vung Tau

– Name of project: Training Center Office of Transport and Communications University – Ho Chi Minh City in Vung Tau
– Investor: Transport and Communications University – Ho Chi Minh City
– Main contractor: Tan Phuoc Thinh Investment & Construction JSC.
– Location of construction: Ward 11, Vung Tau City
– Total value of the package: 18,072,451,879 VND
(In words: Eighteen billion, seventy-two million, four hundred and fifty-one thousand, eight hundred and seventy-nine Dong).
– Construction period: 320 days, from July 14th, 2015
– Construction scale: Main building block (phase 1): 06floors building with terrace, total usable floor area (excluding terrace area): 2,163m2 and other synchronous infrastructure items.